Overview

National Spatial Planning

For the Kozjak pumped storage hydropower plant project on the Drava River and the 2 x 400 kV transmission line connection to the existing international transmission line Maribor-Kainachtal, the Decree on the national spatial plan (DPN) for the pumped storage hydropower plant on the Drava River and the PSP-TS Maribor transmission line connection (Official Gazette of the Republic of Slovenia, No. 12/11) was adopted in 2011on the basis of the elaborated conceptual design (IBE) from 2005 and the positive environmental assessment in the environmental report (VGB, 2007, supplemented June 2010). The national spatial planning determined the spatial layout of the Kozjak Pumped Storage Hydropower Plant, the national spatial planning area, the spatial implementation conditions for the design and the guidelines for the determination of the intended use of space in the municipal implementation acts for the area.

The DPN covers an area of approximately 280 hectares. Of this area, we can distinguish the following segments:

The remaining 24 hectares consist of access roads and the intersection area planned for reconstruction in Spodnja Selnica.

The figure below shows a graphical representation of the area of the Decree on the national spatial plan for the Kozjak pumped storage hydropower plant on the Drava River and the PSP-TS Maribor transmission line connection and its spatial layout. 

Slika_5

Kozjak PSP project and local self-government (municipalities)

As can be seen in the figure above, the Kozjak pumped storage hydropower plant project and the 2 x 400 kV transmission line link geographically extend across three municipalities: Selnica ob Dravi, Maribor and Pesnica.

The largest construction works will be carried out in the Municipality of Selnica ob Dravi, where all key components of the pumped storage hydropower plant are to be built (upper storage basin, penstock, transformer and powerhouse cavern, discharge pipeline, access and service tunnel, surge tank, inlet-outlet structure, and part of the transmission line) and the necessary reconstruction of the access roads to the upper storage basin.

In the Municipality of Maribor, the construction of the transmission line and the creation of a mitigation area is planned. In the Municipality of Pesnica, the construction of the termination of the transmission line and the connection into the existing Maribor-Kainachtal transmission line is planned.

The total length of the transmission line is 21.7 kilometres and includes 70 standpoints, of which:

The project affects approximately 542 properties in the Municipality of Selnica ob Dravi, 424 in the Municipality of Maribor and 145 in the Municipality of Pesnica. The lands where permanent occupation is foreseen are scheduled for acquisition. These are mainly lands in the area of the upper storage basin and the lower platform with the inlet-outlet structure and in the area of mitigation measures.

The easements will be acquired on the road surfaces and the standpoints of the transmission line.


Project Investors

The project for the construction of the Kozjak PSP and the 2 x 400 kV transmission line has two investors. They are two well-known and trusted Slovenian companies: Dravske elektrarne Maribor, d.o.o. and ELES, d.o.o., the operator of the combined transmission and distribution electricity network.


Project implementation plan

Project phases

The Kozjak PSP project is divided into four phases:


Pre-investment phase

The pre-investment phase covers all activities in the period leading up to the award of the building permit under the integral procedure (IGD), including the preparation of project documentation, obtainment of the environmental consent (OVS), and the building permit procedure. The key activities of the pre-investment phase are:


Implementation phase

The implementation phase covers all the activities necessary for the realisation of the project after obtaining the integral building permit. The implementation phase consist of: preparatory works, access roads, construction works on all parts of the Kozjak PSP facility (I-O facility, switchyard, all tunnels and pipelines, both caverns, surge tank, storage basin), supply and installation of all electrical, mechanical and hydromechanical equipment, construction of the 400 kV transmission line, provision of mitigation measures, all testing, trial operation, elimination of faults within the warranty period and all activities until the facility is granted an usage permit.


Project schedule

Overview of key activities already carried out: 


Key activities planned until the building permit is obtained

The timetable foresees the obtaining of the integral building permit by the end of 2026. In 2027, the implementation phase of the project will start with preparatory works. The following are the more important activities until the end of 2026.

2024:

2025:

2026:


Current project phase and current activities

The project is currently in the pre-investment phase, which means that all the activities necessary to obtain the integral building permit are being carried out.

The main ongoing activity of the project, which is important for the client, the client's engineer, and the external designer, is the revision of the conceptual design. The conceptual design is an update of the preliminary concept and further specifies all the elements of the civil engineering works. Based on the conceptual design, the preparation of project documentation for the obtaining of design and other conditions (DPP) and the preparation of documentation for obtaining a building permit (DGD) will start this year.

All the technical bases to be prepared for the Environmental Impact Assessment (EIA) are in progress or in the procurement phase. The necessary content of the technical bases and the analyses, which examine the impact on the environment and people in more detail, are defined by the adopted Decree on the national spatial plan.

The most important activities include those related to land acquisition or the right to build. Valuations of the real estate to be purchased by DEM as investor for the purpose of the pumped storage hydropower plant are being obtained. On the basis of these valuations, purchase contracts will be concluded with the land owners this and next year.

The aim of Dravske elektrarne Maribor and the state is to build a strategic hydropower facility that will allow the storage of electricity in anticipation of the deployment of solar and other power plants that harness intermittent, renewable resources.